Pool shuts down for $800k repairs

Jasper’s swimming pool was drained on Monday and Tuesday ready for three months of repairs | F.Dragon photo Fuchsia Dragon | [email protected] The slide replacement project is finally off the starting blocks.
Jasper’s swimming pool was drained on Monday and Tuesday ready for three months of repairs  | F.Dragon photo

Fuchsia Dragon | [email protected]

The slide replacement project is finally off the starting blocks.

Jasper Aquatic Centre closed Monday and will remain so for the next three months to allow for the massive operation.

The crumbling old slide and its stairs will be ripped out and replaced, the slide’s landing pool will be deepened, and there will be other general repairs.

The current slide was built in 1988 from yew wood encased in fiberglass, and over time water has leaked into the casing.

“It’s not yew board any more, it’s yew sludge,” said Jeremy Todgham, manager of the Fitness and Aquatic Centre.

“It causes pressure and cracks in the fiberglass.”

He said the last time the slide was inspected in spring 2018, there were “countless” cracks and 74 more were patched. When the repairs only lasted a few months, the slide was shut down for good.

The new slide will be safe, long lasting and higher quality.

It will be the same shape as the current one, but with no tunnel roof, and made from smaller sections that could be more easily replaced.

And it’s not just the slide that’s falling apart.

The slide’s stairs and the metal connections that keep them there are also badly corroded.

Patches of rust are peeling from the structures and everything is being replaced.

Togham said the new slide stairs will be made from fibergrate, which will not corrode.

“It’s designed to keep the water out,” he said.

“The new stairs will collect water and there will be a drain. Instead of walking on the stairs and getting a shower, it will be disposed of.”

And at the other end of the slide, you will get a safer splash when you hit the water.

The landing pool’s sloped floor will be jackhammered and reshaped to level it and meet current regulations.

Around the pool, the deck will be waterproofed and refinished, and raised tiles will be fixed.

And like during the pool’s regular shutdown, everything is getting a good autumn clean.

Jasper Aquatic Centre is scheduled to reopen on December 18.

During the shutdown, the Fitness Centre and bouldering wall will still be open.

Construction cost breakdown:

Demolition - $160,092

Steel structure - $79,352

Waterslide and stairs replacement - $330,938

Landing pool modifications - $38,240

Refinishing deck and landing pool - $14,641

Construction expenses - $53,050

Consultant costs - $73,256

Contingency - $33,816